Case: Mykolaiv
Mineral Fertilizer Terminal
Mykolaiv oblast association “Zelenyi Svit” and shipyard “Okean” versus
the company “Nika-Tera”
Region: Mykolaiv oblast, city of Mykolaiv
Essence of case: Protection of the citizens
right to participation in the environmentally important decisions
Parties: Mykolaiv oblast association “Zelenyi
Svit” and shipyard “Okean”- plaintiffs
company “Nika-Tera” – defendant
Essence of problem: Satisfaction in the
court of the claim to declare invalid the environmental
impact assessment
statement
Main facts:
In 1995 the project, a chemical fertilizer terminal in Mykolaiv, financed
by an Irish-Russian-Ukrainian joint venture was started. On the day the
joint
venture registered to do business, it donated 20 trams and 20 trolley buses
to the city. Local authorities subsequently approved the project, and construction
began in August 1995 in violation of environmental laws requiring that
an "environmental
expertise" be conducted prior to project approval.
The local Ministry of Environmental Protection and Nuclear Safety (EcoSafety)
temporary stopped the construction and ordered the company to conduct an
environmental expertise of the project.
The company then submitted the project to the local Ministry office for environmental
expertise. However, the company did not publish an environmental impact assessment
statement, in violation of the Law on Environmental Expertise. Local ministry
officials subsequently rejected the project on grounds that it had unacceptable
negative environmental impacts. However, the company then requested the national
EcoSafety office in Kyiv to review the local EcoSafety office's environmental
expertise, and officials in Kyiv reached a positive conclusion in their own
environmental expertise, overturning the local ministry office's rejection
of the project.
EPL sued the national EcoSafety office in the High Arbitration
Court, claiming that the environmental expertise it conducted was deficient
on procedural
grounds. The court dismissed the case three times on procedural grounds before
EPL was granted a hearing on the substance of its claims.
EPL represented two clients in the action filed in the High Arbitration
Court: Zelenyi Svit (Green World), an environmental non-governmental organization;
and a shipbuilding company that claimed that the health of its workers would
be adversely affected by the terminal. More than 10,000 local citizens also
signed a petition opposing the project. By the conclusion of the case, this
number had increased to 100,000. including members of representative bodies
such as local co-operatives and labor unions.
In its lawsuit, EPL claimed that the ministry's expertise was invalid
primarily on the following grounds. The Ministry failed to require the company
to publish the environmental impact assessment statement prior to commencement
of the environmental expertise, thereby depriving the public of the opportunity
to participate meaningfully in the process. Moreover, the construction of
the project began before the ministry completed its expertise. This is strictly
prohibited under the Law on Environmental Expertise. This premature construction
complicated matters because significant funds had been invested in the project
by the time the case reached the courts, making it more difficult for a judge
to invalidate the expertise and order that work on the project cease. The
ministry
failed to publish the conclusion of the environmental expertise as well as
to take public opinion into account as required under the Law on Environmental
Expertise. In the face of 100.000 citizens
voicing opposition to the project and public expertise that found the project
to be unsuitable, the ministry still approved the project. The expertise
conclusion did not identify the experts who participated in the expertise,
thereby depriving
citizens of the ability to challenge their qualifications, in violation of
the Expertise Law. The ministry failed to consider adequately the negative
environmental impacts associated with the project, including, but not limited
to, possible impacts on endangered species, the surrounding estuary, and
pre-existing elevated contaminant levels in the South Bug River.
Judge G. ruled in favor of EPL and ordered the ministry to require
the company to cease work on the project. The court exercised its authority
under the Law on Environmental Expertise to find the conclusions of the expertise
invalid when procedural requirements are violated. The court found that the
environmental impact assessment statement was published two months after
the expertise was completed, in violation of the public's right to be informed
and to participate in the expertise process.
The ministry argued that its failure to publish the EIA statement had not
affected the outcome of the expertise because the public had known about
the project.
The court rejected this argument outright because the Expertise Law does
not provide for substitution of the notice requirement. Without notice of
the expertise,
the court observed, the public could not fully take part in the process.
The case has not been finalized yet. The Ministry appealed and the court
decision was canceled. But even the first stage victory offers hope for citizens
that
their environmental rights can be upheld. |